July–August Execution Plan

Planning Jul 13–17 · Execution Jul 20 – Aug 7 · QA buffer Aug 10–14 · 33 workstreams · 10 builders · Board = source of truth
✓ COMMITTED EXECUTION PLAN — published Jul 24. Estimates validated against the GitHub board (source of truth). Changes go through the board and the weekly go/no-go, not this file.
Lane 1 · Explainability chain Lane 2 · Collective Intelligence P1 build Customer-dated Process / planning Stretch — first to cut
How to read (updated Jul 24): tasks per person with live status chips (board = source of truth). Capacity bars show the original window plan; the verdict line shows REMAINING work vs the ~10 days left (Jul 27 – Aug 7), counting in-progress items at 50%. E1/E2/E4 QA-wave estimates come from the board and need verification at Monday's go/no-go.
Timeline by person. Higher-priority items are front-loaded; dependencies sequenced so nothing blocks (spikes & decision docs close in planning week; consumers start after). Hover a bar for the full label. Red ▼ marks hard external dates.
Timeline by workstream. Same bars, grouped by the 29 workstreams — shows where streams hand off and where they converge.